SpaceX (xAI)Memphis, Tennessee
Operating100% built

Running (some may still be expanding)

340 MW
Planned power (est.)
340 MW
Running now (satellite)
$13B
Investment (estimated)
2025
Full build-out

Colossus 1 is an AI data center in Memphis, Tennessee, developed or operated by SpaceX (xAI) for Anthropic. Satellite imagery shows its computers drawing about 340 MW today.

Location
3231 Riverport Rd, Memphis, TN 38109
Developer / owner
AI users / tenants
Electric utility / energy
Water
Not disclosed
Chips
H100, H200, B200
First public record
Apr 24, 2024
Home electricity price in Tennessee, August 2026
13.4¢per kWh+2.5% vs. August 2025

U.S. average: 18.2¢ (+3.4%).

Statewide context, not this project’s effect: prices move for many reasons. Source: U.S. Energy Information Administration.

On the public record
  • Water: Allocation (Nov 5, 2026, Memphis Light, Gas and Water)
  • Environmental permit: Approved, under challenge (Jul 2025, Shelby County Health Department)