What changed
Construction updates and decisions, newest first. Data updated Nov 15, 2026.
Nov 2026
- Nov 5, 2026 · Meta Aiken, SC · Satellite analysis by Epoch AI
Building 2 is operational assuming a 3 month lag compared to Building 1.
- Nov 1, 2026 · OpenAI Stargate Abilene, TX · Satellite analysis by Epoch AI
Buildings 7-8 are estimated to be operational. On March 24, Building 8 roughly looked like where Building 3 was in September. Building 3 is estimated to be operational in April, 7 months later. This naively suggests Building 8 will be operational by early November, 7 months after March 24. Oracle gave no date for the last two buildings on its September 10 call.
Oct 2026
- Oct 31, 2026 · Anthropic Lake Mariner, NY · Satellite analysis by Epoch AI
Building 2 (AKA CB4) is operational. On February 26, Terawulf stated that CB4 was expected to be energized by Q3 2026.
- Oct 26, 2026 · Meta Los Lunas, NM · Satellite analysis by Epoch AI
Building 2 (a tent like building) is operational. Based on a default estimate of 3 months for fit-out after structural completion in July.
- Oct 23, 2026 · QTS Cedar Rapids, IA · Satellite analysis by Epoch AI
Buildings 1–3 look externally complete, with the air-cooled chillers fully installed, and surrounding yard work cleared. The many cars and trucks parked beside the buildings suggest commissioning is still underway, so we’re not counting any buildings operational yet. Buildings 4-6 shells appear complete, and Building 7 is nearly 90% roofed. This is based on high-resolution satellite imagery from this date.
- Oct 19, 2026 · Anthropic-Amazon New Carlisle, IN · Satellite analysis by Epoch AI
Buildings 17-18 are operational. This is an estimate based on a rule of thumb of "operational 5 months after roof is complete", assuming the roofs took one more month after 2025-12-23. Also added four more months to account for commissioning and adjacent cooling units not being complete yet.
Sep 2026
- Sep 30, 2026 · Meta Temple, TX · Satellite analysis by Epoch AI
Building 3 is operational. Based on the stated completion date in this regulatory filing
- Sep 10, 2026 · OpenAI Stargate Abilene, TX · Satellite analysis by Epoch AI
Buildings 5-6 are operational. On Oracle's Q1 FY27 earnings call (September 10, 2026), Clay Magouyrk said "6 of the 8 campus buildings, representing 618 megawatts and 75% of total capacity have now been delivered to the customer" (transcript). 618 MW = 6 x 103 MW, matching the per-building IT power figure Crusoe reported earlier. Since Oracle is the chip owner rather than the facility operator, we assume "delivered" means the chips are installed and ready to use.
- Sep 6, 2026 · Google Pryor (North), OK · Satellite analysis by Epoch AI
Building 2 is operational, confirmed via RAAD drone imagery of spinning cooling tower fans on September 8th.
- Sep 4, 2026 · OpenAI Stargate Shackelford, TX · Satellite analysis by Epoch AI
Buildings 1-5 shells complete and fully roofed. Buildings 1-3 appear to be actively installing cooling and backup generators nearby. The pads for Buildings 6-10 to the north have also been visibly cleared, with foundations for Buildings 6 and 7 underway.
- Sep 1, 2026 · CoreWeave Denton TX, TX · Satellite analysis by Epoch AI
Building 8 interior fit-out scheduled to begin. TDLR project TABS2026028247 schedules a $110M interior fit-out of the existing 27,678.22 sq ft Building A as a data hall beginning September 1, 2026.
Aug 2026
- Aug 31, 2026 · Meta Prometheus, OH · Satellite analysis by Epoch AI
Buildings 7-10 (tents) are operational, based on infrared drone video from RAAD (raad.com) captured on this date. The video suggests that 138.8 MW of nameplate turbine capacity is operating at the Socrates South power plant (about 69% of the 200 MW nameplate capacity), and Buildings 7-10 roof vents are bright on infrared while Buildings 11-12 vents are not. That's 4/6 buildings operating, implying about 67% of capacity, which is consistent with 69% of the power plant operating. In the north, Buildings 16-27 (tents) look to be in a completed state. Each northern set of 6 tents still awaits to be connected to one of the corresponding power plants to become operational. Drone video from August 19th shows no turbines operating at Socrates North, though there are 3 small diesel generators operating. Building 13 (Vantage) is still under construction, we estimate another 3 months before operability.
- Aug 30, 2026 · Coreweave Helios, TX · Satellite analysis by Epoch AI
Building 1 operational at full capacity. This is based on "Phase I", which is expected to be operational by the end of the first half of 2026. We added two months of overhead to account for remaining construction and/or installation of CoreWeave's chips, since the June 17 image still showed active minor construction around the building.
- Aug 24, 2026 · Meta Gallatin, TN · Satellite analysis by Epoch AI
Building 1 is operational, based on a lack of construction activity around the shell and cooling equipment, and about 6 months passing after structural completion.
- Aug 19, 2026 · Google Fort Wayne, IN · Satellite analysis by Epoch AI
Building 2 has all cooling towers installed and is likely undergoing fit-out and commissioning. So we give it about 3 more months until it's operational. Building 3 appears to be slightly further than Building 2 was in March, so we estimate a 4-month lag.
- Aug 15, 2026 · Google Mesa, AZ · Satellite analysis by Epoch AI
Building 2 is operational. This is estimated based on the close-to-complete construction status from May 2026.
- Aug 7, 2026 · Meta Aiken, SC · Satellite analysis by Epoch AI
Building 1 is confirmed operational via drone imagery with 8/9 group of coolers with spinning fans. Imagery also confirms all cooling and power infrastructure in place for Building 2.
- Aug 5, 2026 · Google Columbus, OH · Satellite analysis by Epoch AI
Confirmation that Building 4 is complete. Building 5 has progressed since February, with a complete roof, all backup generators in place, and five cooling towers in place.
- Aug 2, 2026 · Meta Sarpy, NE · Satellite analysis by Epoch AI
Building 1 is operational (estimate).
- Aug 1, 2026 · Google Kansas City East, MO · Satellite analysis by Epoch AI
Building 1 operational. Estimated based on present construction progress and typical timelines.
- Aug 1, 2026 · AWS Berwick, PA · Satellite analysis by Epoch AI
Building 3 expected to come online sometime around August 2026, since in the May satellite image it appeared structurally complete with minimal construction surrounding it. Basing MW estimate using Building 2 as a reference.
Jul 2026
- Jul 30, 2026 · Anthropic Barber Lake, TX · Satellite analysis by Epoch AI
Building 1 shell is complete, with rooftop units installed, and most air-cooled chillers in place in a ground yard to the north. Most of the 120 backup diesel generators are also in place. Substantial progress since Nov 2025, still under construction and not yet energized.
- Jul 30, 2026 · Meta Bowling Green, OH · Satellite analysis by Epoch AI
Roofs of Buildings 1 and 2 are more than halfway complete. All chillers for both buildings are visible. Construction on Buildings 3 and 4 has begun, with outlines laid. Construction on the Apollo Power Generation Project (a BTM power plant built just to the east of the data center) is in progress, with foundations poured and generation equipment being set in place.
- Jul 30, 2026 · OpenAI Stargate Lordstown, OH · Satellite analysis by Epoch AI
Active construction visible on and around the datacenter, with the roofing mostly in place. This is based on satellite imagery. No buildings operational yet.
- Jul 28, 2026 · OpenAI Stargate Abilene, TX · Satellite analysis by Epoch AI
Buildings 5-8 are structurally complete and roofed but not yet confirmed operational (fit-out ongoing). The substation looks complete.
- Jul 28, 2026 · Meta Los Lunas, NM · Satellite analysis by Epoch AI
Building 2 (a tent-like building) shell is complete, but we don't believe it's operational because there is unpaved ground, no cars parked right in front, the first tent buildings at Meta Prometheus took about 16 months (it's been 10 months for this building). North-west of Building 1, the outline of a building of similar dimensions and style to Meta Jeffersonville's Building 1 is visible, this is labeled as Building 3. West of Building 1 we see more land clearing for what could be a building similar to Meta Jeffersonville's Building 2.
- Jul 25, 2026 · Meta Cheyenne, WY · Satellite analysis by Epoch AI
Both buildings estimated to be operational.
- Jul 24, 2026 · OpenAI Stargate Wisconsin, WI · Satellite analysis by Epoch AI
Construction continues, Buildings 1 and 2 appear roughly halfway roofed, and building 3 foundation is halfway done.
- Jul 23, 2026 · Anthropic Lake Mariner, NY · Satellite analysis by Epoch AI
Building 1 looks complete, consistent with it going operational back in May. Building 2 is mostly complete, with the row of backup generators on the east side of the building still being installed. Building 3 shell is complete, with rooftop coolers midway through installation, and no neighboring generators installed/visible yet.
- Jul 23, 2026 · Core42 Lake Mariner, NY · Satellite analysis by Epoch AI
Both buildings still operational according to satellite imagery.
- Jul 13, 2026 · CoreWeave Lancaster Greenfield site, PA · Satellite analysis by Epoch AI
Cooling install continues on the roof, satellite imagery indicates that not all units have been completed. Continued presence of construction vehicles and unfinished land on the campus suggests that the building is not operational yet.
- Jul 12, 2026 · Microsoft-Nebius New Jersey, NJ · Satellite analysis by Epoch AI
Compared with the April 2026 image, the building shell is closer to completion, and several additional air-cooled chillers have appeared on the ground, though they do not yet appear to be connected or operating. We therefore keep IT capacity at 50 MW.
- Jul 10, 2026 · xAI QTS Atlanta, GA · Satellite analysis by Epoch AI
No significant change to the building since the August 2025 image.
- Jul 7, 2026 · Google Council Bluffs (East), IA · Satellite analysis by Epoch AI
Building 3 is operational. 7 cooling towers were finally installed despite being more spread out compared to the first two buildings. Cooling towers models vary slightly between buildings. Ground clearing to the southwest seems to be setting up for two more buildings.
- Jul 3, 2026 · CoreWeave Denton TX, TX · Satellite analysis by Epoch AI
Buildings 1-7 are operational and running, with no construction work visible. This is based on both satellite imagery, and the Q2 2026 Earnings call stating the campus was operational by midyear 2026.
- Jul 1, 2026 · Google Midlothian, TX · Satellite analysis by Epoch AI
Estimated full completion of the expanded row of cooling towers and backup generators for Building 1.
Jun 2026
- Jun 30, 2026 · Google Omaha, NE · Satellite analysis by Epoch AI
Building 3 is operational (estimate). Based on there being minimal construction work as of May 15.
- Jun 30, 2026 · CoreWeave Ellendale ND, ND · Satellite analysis by Epoch AI
According to satellite imagery, Building 2 is fully roofed and shell complete, with rooftop chillers mostly installed. Building 3 construction is well underway, with about 1/4 of the roofing done and the foundation laid out.
- Jun 22, 2026 · OpenAI Stargate New Mexico, NM · Satellite analysis by Epoch AI
Construction has advanced significantly since February 2026. We observe extensive earthworks and multiple graded building pads across the campus, with structural work underway on the main data center buildings. A large solar array and water storage basins are visible on site, and two cleared areas on the western side of the campus, likely for on-site power generation. No buildings appear operational yet (no completed roofs or signs of active cooling), consistent with the projected 2028 completion.
- Jun 19, 2026 · Meta Rosemount, MN · Satellite analysis by Epoch AI
Buildings 1 and 2 are estimated to be operational.
- Jun 18, 2026 · Meta Montgomery, AL · Satellite analysis by Epoch AI
We estimate Buildings 1 and 2 are operational.
- Jun 17, 2026 · Coreweave Helios, TX · Satellite analysis by Epoch AI
Building 1 appears externally complete and likely Ready for Service, with all cooling/roofing/generators in place, but we're not labeling it operational yet due to visible surrounding yard/construction work. CoreWeave likely still needs time to install chips and use all their designated chip capacity. The pad to the northeast has foundations being laid out for Building 2.
- Jun 16, 2026 · Microsoft Project Osmium, IA · Satellite analysis by Epoch AI
No notable changes since October.
- Jun 16, 2026 · Google Arcola, VA · Satellite analysis by Epoch AI
Building 1 is operational, based off of colored motion artifacts from cooling towers and direct visual verification.
- Jun 15, 2026 · Colossus 2, TN · Satellite analysis by Epoch AI
The site is estimated to have at least ~830 MW of GPU server power, with at least "at least 220,000 additional GB300 processors and over 400 additional megawatts of compute power", corresponding to the "next phase of expansion" found in the following company S-1 filing, page 76. This estimate is backed up by our cooling and turbine based power production calculations. The cooling calculations suggest there is enough infrastructure to support ~850MW of IT Power. Similarly the energy production calculations support ~900MW of available IT Power. This gives us confidence that the proposed expansion was achieved in time. The roof for building 3 is halfway complete.
- Jun 15, 2026 · Colossus 1, TN · Satellite analysis by Epoch AI
No major changes to the data center since February. Solar panels have been placed next to the facility.
- Jun 14, 2026 · Microsoft Fairwater Atlanta, GA · Satellite analysis by Epoch AI
Building 3 and 4 are operational.
- Jun 13, 2026 · CoreWeave Muskogee OK, OK · Satellite analysis by Epoch AI
Based on satellite imagery, Building 1 has completed construction, with adjacent land cleared for what we're assuming will have power substations/generators. We can assume Building 1 is not operational from all the yard work directly surrounding it, and the lack of a parking lot. Building 2 (The one not leased to CoreWeave) is still in land clearing phase.
- Jun 4, 2026 · Amazon Madison Mega Site, MS · Satellite analysis by Epoch AI
Buildings 6 and 7 roof completed. Building 8 roof nearly completed. Building 9 roof half way up. No new operational buildings.
- Jun 4, 2026 · Meta Jeffersonville, IN · Satellite analysis by Epoch AI
Building 1 and 2 are operational.
- Jun 3, 2026 · Anthropic-Amazon New Carlisle, IN · Satellite analysis by Epoch AI
Buildings 17-18 fully roofed but still having surrounding generators/cooling under construction. Cleared land for buildings 19-32 is still bare, with no building foundations visible yet. Based on satellite imagery.
- Jun 2, 2026 · Meta Huntsville, AL · Satellite analysis by Epoch AI
We estimate Building 2 becomes operational due to being 120 days after final phases of construction, 9 months since roof and cooling were done, and similar Meta data centers construction timelines.
- Jun 1, 2026 · Colossus 1, TN · Satellite analysis by Epoch AI
We assume that Anthropic has started using Colossus 1 now, since the announcement said they would get access to 300 MW "within the month" of May.
- Jun 1, 2026 · Meta Kuna, ID · Satellite analysis by Epoch AI
Building 1 and 2 are operational. The 2nd phase of an offsetting solar array goes online on May 31, 2026. Idaho Public Utilities Comission's approval for this start date notes that "[Meta]’s load is expected to increase so much that it will suffer a capacity deficit in June 2026 if served only by Pleasant Valley Solar 1.1,” A redacted table in the staff comments document suggests the data center's load will continue to increase through August, when it presumably reaches the maximum capacity of both buildings.
May 2026
- May 31, 2026 · Anthropic Lake Mariner, NY · Satellite analysis by Epoch AI
Building 1 is operational. On February 26, Terawulf stated that CB3 was expected to be energized by mid-May 2026. A drone video commissioned from RAAD shows several cooling units operating on May 8. It's therefore likely that the building was fully operational around this date.
- May 26, 2026 · Google Pryor (North), OK · Satellite analysis by Epoch AI
Building 2 looks almost complete, but still appears to have three cooling towers missing. We therefore expect another 3 months until full operation.
- May 23, 2026 · OpenAI Stargate Abilene, TX · Satellite analysis by Epoch AI
Buildings 3 and 4 are estimated to be operational. On April 22nd, Oracle posted that "In Abilene, 200MW is already operational". This suggests that there was still only Building 1 and 2 operational. Since Buildings 3 and 4 looked complete from the outside on March 24th, we give it another month after Oracle's post for them to be operational. This would also give the buildings a similar 1 year 4 months timeline that Buildings 1 took from land clearing to being operational.
- May 20, 2026 · Google Bristow, VA · Satellite analysis by Epoch AI
Building 3 is operational, based off of colored motion artifacts from cooling towers.
- May 20, 2026 · CoreWeave Chester VA, VA · Satellite analysis by Epoch AI
Based on satellite imagery, Building 3 has cleared its land and is beginning construction. Building 2 is operational judging from the colored motion artifacts on the cooling tower fans.
- May 18, 2026 · Meta Prometheus, OH · Satellite analysis by Epoch AI
Building 7-11 (Meta tents) look structurally complete but not operational, given there is still construction activity, including at the adjacent Socrates South power plant. Northern tents (Buildings 16-27) are all roofed except for 21 and 27.
- May 18, 2026 · Google New Albany, OH · Satellite analysis by Epoch AI
Building 5 has all cooling towers installed, and all other components look complete, but there is still light work around the building. Based on that, we estimate 3 more months until operational.
- May 18, 2026 · AWS New Albany, OH · Satellite analysis by Epoch AI
Satellite imagery shows Building 1 in the northern campus still appears structurally finished, with no visible change from the prior two months, but we're still not counting it operational due to visible construction work around the perimeter. Buildings 2-3 still have nearby generators/cooling equipment being installed, and Building 4 is only roughly 80% roofed. Eastern campus Buildings 5-9 remain operational. Middle campus Buildings 10, 12, 13, and 14 remain operational; Building 11 is still installing backup generators and is not counted.
- May 15, 2026 · Microsoft Fairwater Atlanta, GA · Satellite analysis by Epoch AI
Building 4 still has some equipment strewn around the perimeter, so we think it is still going through commissioning. Two new buildings at the campus have shells underway, but we don't know if Microsoft is the tenant for those.
- May 15, 2026 · Microsoft Fairwater Wisconsin, WI · Satellite analysis by Epoch AI
The main shell of Building 2 looks almost completed. In Area 2 (northwest of Buildings 1-2), the grading for the original design has been replaced with grading for the new 9-building design, making way for Buildings 3-11. Work continues on the northern substation in Area 2.
- May 15, 2026 · Google Mesa, AZ · Satellite analysis by Epoch AI
Building 2 is close to being operational. There is only construction left on the backup generators, which are almost complete. Some equipment is also strewn around the building, especially near the air-cooled chillers. Preparation seems to have begun for Building 3 at the site.
- May 15, 2026 · Google Omaha, NE · Satellite analysis by Epoch AI
Building 3 appears almost complete, with only minimal construction work and equipment remaining. The cooling towers are spaced apart in an unusual way, but there's no obvious sign that more will be installed before operation. Buildings 4 and 5 haven't started construction yet, the cleared land is still empty.
- May 15, 2026 · Amazon Ridgeland, MS · Satellite analysis by Epoch AI
Buildings 1-4 are operational, based on the buildings shells and backup generators and most of the landscaping looking complete. Building 5 roof is complete but still lacks cooling equipment.
- May 14, 2026 · QTS Richmond 2, VA · Satellite analysis by Epoch AI
Building 5 is estimated to be operational, based on the previous entry.
- May 14, 2026 · QTS Richmond 3, VA · Satellite analysis by Epoch AI
Building 2 and 3 are operational, based on the previous entry.
- May 12, 2026 · Google Lincoln, NE · Satellite analysis by Epoch AI
Building 1 operational. This is based on the fact that is no more visible equipment or construction around the building, and based on previous imagery and when construction started on the last pieces of equipment (fans). Building 2's roof is complete, with generator construction more than halfway complete and cooling construction beginning. Electrical equipment on the side of Building 2 is also around halfway complete.
- May 7, 2026 · QTS Cedar Rapids, IA · Satellite analysis by Epoch AI
Similar to April, Buildings 1-3 shells look complete. Buildings 4-6 are still far along, and the eastern Building 7 foundation is still underway.
- May 6, 2026 · Colossus 1, TN · Satellite analysis by Epoch AI
Anthropic announces their agreement with SpaceX to use all of the compute capacity at Colossus 1. They state that this corresponds to more than 300 MW (presumably IT power) and over 220,000 GPUs. This is slightly different to previous reports adding up to 230,000 GPUs, but still roughly consistent with our estimates.
- May 6, 2026 · CoreWeave Marble NC, NC · Satellite analysis by Epoch AI
Core Scientific said Marble was fully handed over to CoreWeave with about 65 MW of billable customer power online.
- May 5, 2026 · AWS Berwick, PA · Satellite analysis by Epoch AI
Buildings 1 and 2 visibly complete and operational. Building 3 appears complete and may be commissioning, but it's likely not operational yet given the immediate surrounding construction work. Several additional building shells and pads are still in construction, but none are assumed operational due to all the construction work visible. This is based on satellite imagery from this date.
- May 4, 2026 · Google Papillion, NE · Satellite analysis by Epoch AI
Building 4 shell mostly complete, Building 5 steel framing is underway.
- May 4, 2026 · Meta Sarpy, NE · Satellite analysis by Epoch AI
Building 1 shell, electrical and cooling equipment looks complete, with minimal construction work, so we expect it to be operational within 3 months.
- May 2, 2026 · Meta Eagle Mountain, UT · Satellite analysis by Epoch AI
Satellite image shows strong evidence that Buildings 1 and 2 are operational: colored motion artifacts on many cooling fans, plus cars parked at the building entrances.
- May 2, 2026 · QTS Eagle Mountain, UT · Satellite analysis by Epoch AI
Building 1 roof finished. Satellite imagery shows construction vehicles and concrete pads with no air cooled chiller units indicating Buildings 1 and 2 cooling install continues. On the other side of each building, emergency generator install continues as well.
- May 1, 2026 · Google Columbus, OH · Satellite analysis by Epoch AI
Building 4 operational. No more visible construction, and since only 3 fans needed to be installed since Feburary, operational date was likely soon after. Building 5 roof almost complete.
- May 1, 2026 · Stream Phoenix, AZ · Satellite analysis by Epoch AI
Estimated: AI building 1 should be operational. Major construction work finished by January 31, 2026, and the shell looked complete by that date. We estimate after three months the building will be operational.
Coming up
Scheduled hearings and decisions
- Dec 2026Meta HyperionLouisiana Public Service Commission: Entergy’s request for seven more gas plants (about 5.3 GW) for the expansion awaits a commission decision expected in December 2026.
Construction updates from satellite imagery via Epoch AI (CC BY 4.0), plus records compiled for this site. The data refreshes automatically each week.