Google Omaha
Running (some may still be expanding)
Google Omaha is an AI data center in Omaha, Nebraska, developed or operated by Google for Google DeepMind. Satellite imagery shows its computers drawing about 237 MW today, against 395 MW planned.
U.S. average: 18.2¢ (+3.4%).
Statewide context, not this project’s effect: prices move for many reasons. Source: U.S. Energy Information Administration.
Satellite figures are Epoch AI estimates from imagery of buildings, cooling and power equipment; about 80% fall within a factor of 1.4 of the true value.
- Jul 23, 2028ScheduledSatellite analysis by Epoch AI · 395 MW planned
Building 5 is operational. We expect a 5th building because there's enough land cleared for one. We assume a roughly 6-month delay after Building 4.
- Jan 23, 2028ScheduledSatellite analysis by Epoch AI · 316 MW planned
Building 4 is operational. Expect a 4th building because there's enough land cleared for it. Assuming the foundation starts at the end of May 2026 and it takes a similar time to Building 3 from foundation to operational (1 year 8 months).
- Jun 30, 2026Satellite analysis by Epoch AI · 237 MW in use
Building 3 is operational (estimate). Based on there being minimal construction work as of May 15.
- May 15, 2026Satellite analysis by Epoch AI · 158 MW in use
Building 3 appears almost complete, with only minimal construction work and equipment remaining. The cooling towers are spaced apart in an unusual way, but there's no obvious sign that more will be installed before operation. Buildings 4 and 5 haven't started construction yet, the cleared land is still empty.
- Oct 21, 2025Satellite analysis by Epoch AI · 158 MW in use
Building 3 has all backup generators in place but they are still being installed. Two cooling towers have fans on them, with more underway. To the south of Building 3, more land has been cleared and there's a new carpark. This suggests another building will soon start construction.
- Apr 21, 2025Satellite analysis by Epoch AI · 158 MW in use
Confident that Building 2 is operational
- Mar 16, 2025Satellite analysis by Epoch AI · 158 MW in use
Confirmation that there's no obvious construction happening for Building 2. Building 3 roof started.
- Nov 19, 2024Satellite analysis by Epoch AI · 158 MW in use
Building 2 is operational, based on it being 8 months since the roof was complete, and surrounding infrastructure looks just completed (finishing the cooling towers).
- Jul 29, 2024Satellite analysis by Epoch AI · 79 MW in use
Building 2 has 3 cooling towers installed.
- Apr 8, 2024Satellite analysis by Epoch AI · 79 MW in use
Building 1 operational, based on it being 6 months after roof was complete, infrastructure looked complete for 5 months.
- Nov 25, 2021Satellite analysis by Epoch AI · 0 MW in use
Land clearing begins.
No hearings, court cases, approvals or disputes are on record for this project yet.
| Chip | Designer | Units | As of | Count is |
|---|---|---|---|---|
| TPU v5e | 263,957 | Nov 19, 2024 | Estimate | |
| TPU v5p | 47,061 | Nov 19, 2024 | Estimate | |
| TPU v6e | 28,846 | Jun 30, 2026 | Estimate | |
| TPU v7 | 41,901 | Jun 30, 2026 | Estimate |
Source: Epoch AI, AI data centers, CC BY 4.0
Satellite and capacity estimates via Epoch AI (CC BY 4.0)
- Draft basis of air permit with details of cooling towers drive.google.com
- 2025 Environmental Report sustainability.google
- Epoch AI calculation sheet for this site
Satellite estimates: Epoch AI, CC BY 4.0, reformatted for this page.