Meta HyperionLouisiana · State
Louisiana Public Service Commission
Entergy’s request for seven more gas plants (about 5.3 GW) for the expansion awaits a commission decision expected in December 2026.
Votes, tax breaks, permits, water allocations and lawsuits involving AI data centers.
Covers the largest projects so far. Not a complete list.
Louisiana Public Service Commission
Entergy’s request for seven more gas plants (about 5.3 GW) for the expansion awaits a commission decision expected in December 2026.
State district court, Baton Rouge
Landowners and advocacy groups challenge the commission's fast-track approval process for the power projects.
Memphis Light, Gas and Water
Water allocation of up to 1.28 million gallons per day; usage has not reached the cap. A pledged $80M wastewater recycling plant has been on hold since April 2026.
Meta's counsel (per CNBC)
Water allocation could ramp to 8 million gallons/day by 2031; Meta says closed-loop cooling uses zero water most of the year.
Madison County Board
Enterprise zone rules amended to exclude data centers from state incentives.
Lowndes County Commission (3–2)
20-year abatement halving non-school county taxes. Two residents sued the commission on Oct. 18, 2026.
Champaign County Board (unanimous)
Resolution prohibiting tax abatements for hyperscale data centers.
Doña Ana County Commission (unanimous)
Commissioners authorized notice of a potential breach of the bond agreements over the proposed power-generation plan. No breach was declared.
Village of Mount Pleasant
Site sits in Tax Incremental District No. 5 (created for Foxconn). A 42% incremental tax rebate capped at $5M/year was redirected by Microsoft back to the village.
Local reporting
Local officials and reporting link the construction workforce influx to a housing shortage and rent increases in Abilene.
Louisiana Public Service Commission (3–1)
The commission overruled its judge's order requiring Meta to disclose how it calculated job and electricity projections.
Arizona Legislature / Governor
New applications for the data center sales tax exemption barred July 2026 to June 2029; existing certifications unchanged.
Residents, state reporting
Residents and officials question water supply for a large campus in the desert.
Birmingham Industrial Development Board (unanimous)
30-year abatements of 80% of construction taxes and 65% of non-education property tax, ~$3.23B, on a $35.89B investment.
Alabama Legislature (102–0, 32–0)
Act 2026-573 caps data center abatements at 20 years (30 with a community agreement).
U.S. District Court, N.D. Mississippi
NAACP Clean Air Act suit over gas turbines powering Colossus 2. The U.S. Department of Justice intervened and moved to dismiss in June 2026.
Wisconsin Public Service Commission (unanimous)
Rate plan requiring data centers to pay 100% of the cost of infrastructure built to serve them.
Guadalupe County Commissioners (3–2)
Voted down a $500M property tax abatement for a proposed campus in New Braunfels.
Brevard County Commission (unanimous)
Ordinance making data centers ineligible for the county ad valorem tax exemption program.
Michigan Public Service Commission (unanimous)
Conditional approval of DTE Energy contracts for a 1,383 MW load. The Attorney General is appealing.
Saline Township Board
Board voted against rezoning in Sept. 2025, then settled in October after being sued by landowners and developer Related Digital.
Doña Ana County Commission (4–1)
Industrial revenue bonds up to ~$165B. Instead of property taxes, ~$360M in payments over 30 years. Two lawsuits seek judicial review.
Louisiana Public Service Commission (4–1)
Approved Entergy Louisiana building three combined-cycle gas plants to serve the data center.
Shelby County Health Department
Air permit approved for 15 gas turbines powering the site. Environmental groups are challenging the permit.