Meta Rosemount
Running (some may still be expanding)
Meta Rosemount is an AI data center in Rosemount, Minnesota, developed or operated by Meta for Meta. Satellite imagery shows its computers drawing about 178 MW today.
U.S. average: 18.2¢ (+3.4%).
Statewide context, not this project’s effect: prices move for many reasons. Source: U.S. Energy Information Administration.
Satellite figures are Epoch AI estimates from imagery of buildings, cooling and power equipment; about 80% fall within a factor of 1.4 of the true value.
- Jun 19, 2026Satellite analysis by Epoch AI · 178 MW in use
Buildings 1 and 2 are estimated to be operational.
- Mar 21, 2026Satellite analysis by Epoch AI · 0 MW in use
Both buildings and their cooling infrastructure look complete, but the site probably is likely still under commissioning, and few cars are parked to the right of Building 1. We give another 3 months before it's operational.
- Feb 1, 2024Satellite analysis by Epoch AI · 0 MW in use
Land clearing begins.
No hearings, court cases, approvals or disputes are on record for this project yet.
| Chip | Designer | Units | As of | Count is |
|---|---|---|---|---|
| B200 | Nvidia | 85,364 | Jun 19, 2026 | Estimate |
Source: Epoch AI, AI data centers, CC BY 4.0
Satellite and capacity estimates via Epoch AI (CC BY 4.0)
- Official Meta announcement. datacenters.atmeta.com
- Air quality permit for initial buildout. drive.google.com
- Epoch AI calculation sheet for this site
Satellite estimates: Epoch AI, CC BY 4.0, reformatted for this page.