CoreWeave Denton TX
Running (some may still be expanding)
CoreWeave Denton TX is an AI data center in Denton, Texas, developed or operated by CoreWeave for OpenAI. Satellite imagery shows its computers drawing about 262 MW today, against 282 MW planned.
U.S. average: 18.2¢ (+3.4%).
Statewide context, not this project’s effect: prices move for many reasons. Source: U.S. Energy Information Administration.
Satellite figures are Epoch AI estimates from imagery of buildings, cooling and power equipment; about 80% fall within a factor of 1.4 of the true value.
- May 31, 2027ScheduledSatellite analysis by Epoch AI · 282 MW planned
Building 8 projected operational. TDLR project TABS2026028247 schedules Building A's data-hall fit-out for completion by this date.
- Sep 1, 2026Satellite analysis by Epoch AI · 262 MW in use
Building 8 interior fit-out scheduled to begin. TDLR project TABS2026028247 schedules a $110M interior fit-out of the existing 27,678.22 sq ft Building A as a data hall beginning September 1, 2026.
- Jul 3, 2026Satellite analysis by Epoch AI · 262 MW in use
Buildings 1-7 are operational and running, with no construction work visible. This is based on both satellite imagery, and the Q2 2026 Earnings call stating the campus was operational by midyear 2026.
- Mar 2, 2026Satellite analysis by Epoch AI · 131 MW in use
Buildings 1-3 (Denton North) are fully operational running AI (Denton North at 90 MW, Denton South partially running at 41). This is according to an earnings call from this date.
- Feb 23, 2026Satellite analysis by Epoch AI · 131 MW in use
Buildings 1-3 (Denton North) are largely built out/operational, and Denton South has its first data hall plus support equipment substantially installed. Remaining Denton South buildings (4-7) still under construction. This is according to satellite imagery.
- Dec 31, 2025Satellite analysis by Epoch AI · 67 MW in use
Half the campus energized. 67 billable MW are now dedicated to CoreWeave's GPUs across three buildings.
- May 31, 2025Satellite analysis by Epoch AI · 8 MW in use
First 8 MW billable tranche dedicated to AI starts running at the site, with another 40 scheduled by the end of the quarter.
- Nov 1, 2024Satellite analysis by Epoch AI · 0 MW in use
Construction start - The Texas Department of Licensing and Regulation reports Core Scientific is converting existing Bitcoin mining buildings into AI data centers, planning to build AROUND the existing Denton Energy Center.
No hearings, court cases, approvals or disputes are on record for this project yet.
| Chip | Designer | Units | As of | Count is |
|---|---|---|---|---|
| B200 | Nvidia | 100,000 | Jul 3, 2026 | Estimate |
Source: Epoch AI, AI data centers, CC BY 4.0
Satellite and capacity estimates via Epoch AI (CC BY 4.0)
- Core Scientific - CoreWeave Announce 1.2B expansion in Denton, TX investors.corescientific.com
- Core Scientific - Denton Datacenter Official Site corescientific.com
- TMF - Core Scientific Q4 2025 Earnings Transcript fool.com
- WSJ - plans to rent to OpenAI wsj.com
- Epoch AI calculation sheet for this site
Satellite estimates: Epoch AI, CC BY 4.0, reformatted for this page.