Know Your Data Center

CoreWeave

Owner / developerCompute supplier
8
Linked sites
637 MW
Power running at those sites
1.7 GW
Power planned
1
Deals tracked

Sites

Totals count every site the company is linked to, in any role

ProjectRoleLocationNowPlannedComputeStatus
Coreweave HeliosOwnerAfton, TX132 MW528 MW160KOperating · expanding25% built
CoreWeave Ellendale NDOwnerEllendale, ND68 MW400 MW93KOperating · expanding17% built
CoreWeave Denton TXOwnerDenton, TX262 MW282 MW253KOperating · expanding93% built
CoreWeave Muskogee OKOwnerMuskogee, OK—153 MW—Under construction0% built
CoreWeave Chester VAOwnerChester, VA82 MW113 MW88KOperating · expanding73% built
CoreWeave Lancaster Greenfield siteOwnerLancaster, PA—92 MW—Under construction0% built
CoreWeave Marble NCOwnerMarble, NC65 MW65 MW79KOperating100% built
CoreWeave Dalton 1 & 2OwnerDalton, GA28 MW28 MW32KOperating100% built

Deals

  • OpenAI × CoreWeaveDisclosed

    Sep 25, 2025 · Cloud capacity · $22B

    Contracts totalling about $22.4B after a $6.5B expansion of the March 2025 deal. tomtunguz.com