Meta Cheyenne
Running (some may still be expanding)
Meta Cheyenne is an AI data center in Cheyenne, Wyoming, developed or operated by Meta for Meta. Satellite imagery shows its computers drawing about 152 MW today, against 207 MW planned.
U.S. average: 18.2¢ (+3.4%).
Statewide context, not this project’s effect: prices move for many reasons. Source: U.S. Energy Information Administration.
Satellite figures are Epoch AI estimates from imagery of buildings, cooling and power equipment; about 80% fall within a factor of 1.4 of the true value.
- Feb 15, 2027ScheduledSatellite analysis by Epoch AI · 207 MW planned
Buildings 3 and 4 are similar in style and size to the ones seen at the Prometheus site, we estimate their operability based on that timeline.
- Jul 25, 2026Satellite analysis by Epoch AI · 152 MW in use
Both buildings estimated to be operational.
- Mar 22, 2026Satellite analysis by Epoch AI · 0 MW in use
Building 1 shell and cooling looks complete, Building 2 roof almost complete.
- Jan 30, 2025Satellite analysis by Epoch AI · 0 MW in use
Structure for Building 1 and 2 under construction.
- May 1, 2024Satellite analysis by Epoch AI · 0 MW in use
Land clearing begins.
No hearings, court cases, approvals or disputes are on record for this project yet.
| Chip | Designer | Units | As of | Count is |
|---|---|---|---|---|
| B300 | Nvidia | 68,367 | Jul 25, 2026 | Estimate |
Source: Epoch AI, AI data centers, CC BY 4.0
Satellite and capacity estimates via Epoch AI (CC BY 4.0)
- Meta Introduction to the Cheyenne Project datacenters.atmeta.com
- Fortis Construction announcement fortisconstruction.com
- Press announcement suggesting a 2027 operational date cheyenneleads.org
- Epoch AI calculation sheet for this site
Satellite estimates: Epoch AI, CC BY 4.0, reformatted for this page.