STACK Infrastructure NVA02
Running (some may still be expanding)
STACK Infrastructure NVA02 is an AI data center in Manassas, Virginia, developed or operated by STACK Infrastructure. Satellite imagery shows its computers drawing about 85 MW today, against 348 MW planned.
U.S. average: 18.2¢ (+3.4%).
Statewide context, not this project’s effect: prices move for many reasons. Source: U.S. Energy Information Administration.
Satellite figures are Epoch AI estimates from imagery of buildings, cooling and power equipment; about 80% fall within a factor of 1.4 of the true value.
- Jan 1, 2028ScheduledSatellite analysis by Epoch AI · 348 MW planned
Estimate: All 6 AI data center buildings will be finished in 2028, assuming a groundbreak-to-operational timeline of 18-24 months. One is complete, three are clearly under construction, and the last two data centers are still breaking ground and laying foundations.
- Feb 14, 2026Satellite analysis by Epoch AI · 85 MW in use
All buildings have begun construction (with groundwork starting for AI building 6), as depicted by satellite imagery.
- Oct 1, 2024Satellite analysis by Epoch AI · 85 MW in use
Building 1 is operational, which is assumed to be three months after the last backup diesel generators are finished. The generators were first seen to be finished July 1 from satellite imagery (a clear image of this can be seen on July 29 via Google Earth).
- Oct 19, 2019Satellite analysis by Epoch AI · 0 MW in use
Land clearing begins by Peterson Companies for Stack Infrastructure, which is noted in the news and visible on satellite imagery.
No hearings, court cases, approvals or disputes are on record for this project yet.
| Chip | Designer | Units | As of | Count is |
|---|---|---|---|---|
| H100 | Nvidia | 60,911 | Oct 1, 2024 | Estimate |
Source: Epoch AI, AI data centers, CC BY 4.0
Satellite and capacity estimates via Epoch AI (CC BY 4.0)
Satellite estimates: Epoch AI, CC BY 4.0, reformatted for this page.