Google Red Oak
Running (some may still be expanding)
Google Red Oak is an AI data center in Red Oak, Texas, developed or operated by Google. Satellite imagery shows its computers drawing about 77 MW today, against 154 MW planned.
U.S. average: 18.2¢ (+3.4%).
Statewide context, not this project’s effect: prices move for many reasons. Source: U.S. Energy Information Administration.
Satellite figures are Epoch AI estimates from imagery of buildings, cooling and power equipment; about 80% fall within a factor of 1.4 of the true value.
- Dec 1, 2026ScheduledSatellite analysis by Epoch AI · 154 MW planned
Building 2 is estimated to be operational.
- Feb 6, 2026Satellite analysis by Epoch AI · 77 MW in use
Building 1 appears active - the surrounding land is finished including the site entrance and the parking lot. The dry coolers for Building 2 are nearly complete although the building is still clearly a construction zone. The Building 2 substation also appears complete.
- Aug 25, 2025Satellite analysis by Epoch AI · 77 MW in use
Building 1 is operational, based on a Google Earth image showing a completed building shell and equipment, and the large construction car park being emptied. Building 2 shell looks mostly completed.
- Apr 30, 2023Satellite analysis by Epoch AI · 0 MW in use
First signs of development/land clearing
No hearings, court cases, approvals or disputes are on record for this project yet.
| Chip | Designer | Units | As of | Count is |
|---|---|---|---|---|
| TPU v6e | 116,560 | Aug 25, 2025 | Estimate |
Source: Epoch AI, AI data centers, CC BY 4.0
Satellite and capacity estimates via Epoch AI (CC BY 4.0)
Satellite estimates: Epoch AI, CC BY 4.0, reformatted for this page.