Google Storey County
Running (some may still be expanding)
Google Storey County is an AI data center in Storey County, Nevada, developed or operated by Google for Google DeepMind. Satellite imagery shows its computers drawing about 161 MW today, against 300 MW planned.
U.S. average: 18.2¢ (+3.4%).
Statewide context, not this project’s effect: prices move for many reasons. Source: U.S. Energy Information Administration.
Satellite figures are Epoch AI estimates from imagery of buildings, cooling and power equipment; about 80% fall within a factor of 1.4 of the true value.
- Jun 30, 2027ScheduledSatellite analysis by Epoch AI · 300 MW planned
Building 3 is estimated to be operational. We estimate the operational date by analogy to the time that Building 1 took to go from a foundation to being operational. The power capacity is based on the number of generators reported in an air quality permit application (p.92-93). The dry cooler array is more than double the size of the Building 1 array, which suggests an even larger power capacity than we estimate, but we believe the generator-based estimate is more reliable here.
- Apr 13, 2026Satellite analysis by Epoch AI · 161 MW in use
Building 3 has a partially complete shell, electrical and mechanical equipment. Building 4 foundation is underway.
- Sep 28, 2025Satellite analysis by Epoch AI · 161 MW in use
Building 3 foundation is underway. Building 2 exterior looks totally clean/landscaped.
- Jun 30, 2025Satellite analysis by Epoch AI · 161 MW in use
Building 2 is operational. Based on a Google Earth image showing complete building shell, mechanical equipment and generators, plus cars parked at the front.
- Mar 11, 2025Satellite analysis by Epoch AI · 81 MW in use
Building 2 now has generators in place, but there is still a crane and construction work present.
- Aug 30, 2023Satellite analysis by Epoch AI · 81 MW in use
Building 1, which was first operational in 2021, has increased power capacity by about 75%. This is based on the expansion of the dry cooling array from 4 to 7 columns (seen on Google Earth). Its backup generators also grew from 18 to 33, an 83% increase. Around this time (2023 Q3) the quarterly PUE of the campus is 1.24, down from the initial 1.29 in 2022 Q3. Since no other buildings have been added, these changes indicate an increase in power density, which may entail a new generation of hardware getting installed.
- Mar 18, 2019Satellite analysis by Epoch AI · 0 MW in use
Land clearing begins.
No hearings, court cases, approvals or disputes are on record for this project yet.
| Chip | Designer | Units | As of | Count is |
|---|---|---|---|---|
| TPU v5e | 153,165 | Aug 30, 2023 | Estimate | |
| TPU v4 | 34,609 | Aug 30, 2023 | Estimate | |
| TPU v6e | 98,179 | Jun 30, 2025 | Estimate | |
| TPU v5p | 16,521 | Jun 30, 2025 | Estimate |
Source: Epoch AI, AI data centers, CC BY 4.0
Satellite and capacity estimates via Epoch AI (CC BY 4.0)
- Air quality permit application listing emergency generators and a small "R&D" fuel cell plant ndep-onbase.nv.gov
- Aterio aterio.io
- Google data center page datacenters.google
- Epoch AI calculation sheet for this site
Satellite estimates: Epoch AI, CC BY 4.0, reformatted for this page.