OpenAI Stargate Milam
Being built
OpenAI Stargate Milam is an AI data center in Milam County, Texas, developed or operated by SoftBank for OpenAI. Satellite imagery shows nothing running yet, against 857 MW planned.
U.S. average: 18.2¢ (+3.4%).
Statewide context, not this project’s effect: prices move for many reasons. Source: U.S. Energy Information Administration.
Satellite figures are Epoch AI estimates from imagery of buildings, cooling and power equipment; about 80% fall within a factor of 1.4 of the true value.
- Dec 31, 2028ScheduledSatellite analysis by Epoch AI · 857 MW planned
All buildings finished, site is fully operational. Our reasoning is that examples so far take a median of 2-2.5 years to go from land clearing to 1 GW. This suggests around 2028-01-01 here. However, due to delays being more likely than speedups and the fact that this base rate data is still unproven, the more conservative estimate is made. The current state of the site also supports this estimation.
- Mar 23, 2026Satellite analysis by Epoch AI · 0 MW in use
Steel framing and roofing is underway for Building 1.
- Jan 4, 2026Satellite analysis by Epoch AI · 0 MW in use
Small sections of building foundation construction begins, and land clearing appears to be mostly finished
- Sep 27, 2025Satellite analysis by Epoch AI · 0 MW in use
Land clearing begins for the site
No hearings, court cases, approvals or disputes are on record for this project yet.
Source: Epoch AI, AI data centers, CC BY 4.0
Satellite and capacity estimates via Epoch AI (CC BY 4.0)