Microsoft Goodyear
Running (some may still be expanding)
Microsoft Goodyear is an AI data center in Goodyear, Arizona, developed or operated by Microsoft for OpenAI, Microsoft. Satellite imagery shows its computers drawing about 202 MW today.
U.S. average: 18.2¢ (+3.4%).
Statewide context, not this project’s effect: prices move for many reasons. Source: U.S. Energy Information Administration.
Satellite figures are Epoch AI estimates from imagery of buildings, cooling and power equipment; about 80% fall within a factor of 1.4 of the true value.
- Apr 27, 2026Satellite analysis by Epoch AI · 202 MW in use
Foundations appear to be underway for Building 5 and 6, just north of Building 4.
- Nov 12, 2025Satellite analysis by Epoch AI · 202 MW in use
Confirmation that Building 3 and 4 look complete.
- Sep 1, 2025Satellite analysis by Epoch AI · 202 MW in use
Building 3 and 4 operational. Based on interpolating satellite images from Sentinel-2 and Google Earth.
- Jan 16, 2025Satellite analysis by Epoch AI · 81 MW in use
Building 2 operational. Based on interpolating satellite images from Sentinel-2 and Google Earth.
- Apr 24, 2023Satellite analysis by Epoch AI · 40 MW in use
Building 1 operational. Based on interpolating satellite images from Sentinel-2 and Google Earth.
- Jun 21, 2021Satellite analysis by Epoch AI · 0 MW in use
Land clearing begins for Building 1.
No hearings, court cases, approvals or disputes are on record for this project yet.
| Chip | Designer | Units | As of | Count is |
|---|---|---|---|---|
| H100 | Nvidia | 58,302 | Jan 16, 2025 | Estimate |
| B200 | Nvidia | 58,121 | Sep 1, 2025 | Estimate |
Source: Epoch AI, AI data centers, CC BY 4.0
Satellite and capacity estimates via Epoch AI (CC BY 4.0)
- Maricopa County map gis.maricopa.gov
- Dust control permit edms.maricopa.gov
- SemiAnalysis article newsletter.semianalysis.com
- Epoch AI calculation sheet for this site